Background Image
Table of Contents Table of Contents
Previous Page  21 / 24 Next Page
Information
Show Menu
Previous Page 21 / 24 Next Page
Page Background

the communication channels open, we

are able to solve issues together, which

make the entire process much smooth-

er,” comments Croghan. “We might be

two different companies, but ultimately

we have formed a team with KONE. We

work jointly towards the same goal and

it has worked out to be a great partner-

ship between both companies.”

According to

Sherif Fayek

, KONE

Canada’s senior vice president of Busi-

ness Development, this is something

that companies in the elevator industry

have sometimes overlooked in the

past. “Elevator companies typically

do not have the best communications

practices, but we want to change that.

I believe KONE is making an effort to

be a better communicator, not only

through our daily verbal conversations

with customers but also with improved

processes and tools.” Fayek adds, "Both

our KONE eOptimum web-based re-

porting system and our field mobility

program are core examples where we

can add direct value to our customers’

operations regardless if they are a multi-

million contracting corporation or a

smaller facility management firm.”

ADDING UNIQUE

VALUE TO THE MIX

When asked what the key elements are

behind a successful partnership, Fayek

agrees with Croghan on the impor-

tance of communication, and also un-

derlines the importance of adding value

for customers.

“KONE and EllisDon worked togeth-

er right from the start. We have a dedi-

cated team that is devoted to adding

value to the partnership and to the suc-

PEOPLE FLOW |

21

cess of this job. Such collaboration from

the get-go enabled us to get the best

possible outcome and to see how we

could optimize EllisDon’s operations on

the construction site,” explains Fayek.

For the project, KONE designated

a specific project manager as well as

an installation site manager in order to

facilitate the exchange of information

between both companies. This ensured

that everything went according to

schedule during construction. In fact,

KONE’s installation manager was allo-

cated an office on the construction site.

“By having KONE’s

Sam Weatherall

on-site during construction, we were

able to be in constant contact with

the contractor and their workers,” says

Chris Plummer

, KONE project manager

for the 183 Wellington Street project.

“We were able to have frequent meet-

ings with the contractor and we were

even able to solve a few of their logisti-

cal problems by offering our expertise

in elevators for construction time use.”

“We knew that this job would in-

volve difficult and complicated aspects.

But with extensive communication and

planning, they became non-events and

everything progressed flawlessly. At

the end of the day, the most impor-

tant thing for the customer is that

their operations go smoothly and on

schedule,” sums up Plummer.

The 183 Wellington Street project is

in the heart of Toronto’s entertain-

ment district and will feature both

hotel suites and luxury residences.

Photo: Design Architect: KPF, Archi-

tect in record: Page+Steele Architects